Port Operations Snapshot at a Glance
- Initial Launch: End-November 2026 at minimum capacity following test runs
- 2027 Milestone: 15 straddle carriers arrive September 2027 for 50% capacity
- Full Capacity Target: Q1 2028 infrastructure completion; mid-2028 full scale
- Operating Model: 100% SLPA-owned operating company with private partnership review
COLOMBO (SriLankaBiz): Sri Lanka will launch partial operations at the Colombo Port East Container Terminal by the end of November 2026 after completing initial equipment test runs, Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku confirmed on Wednesday.
The state-run Sri Lanka Ports Authority (SLPA) will initially operate the deep-water facility at minimum capacity while awaiting the delivery of pending yard handling equipment. Port officials are phasing in berth availability to capture immediate transshipment demand without delaying vessel turnarounds.
East Container Terminal Phased Rollout and Equipment Schedule
According to the Ministry of Ports and Civil Aviation, the East Container Terminal scaling timeline depends directly on straddle carrier procurement. The first batch of 15 straddle carriers is scheduled to arrive in September 2027, bringing terminal infrastructure to 50% operational capacity.
Procurement for the second batch of 15 straddle carriers will conclude within four months of the initial delivery. Civil works and full 100% infrastructure readiness at the East Container Terminal are targeted for the first quarter of 2028, paving the way for maximum commercial throughput by mid-2028.
| Rollout Phase | Target Timeline | Equipment & Capacity Milestone |
|---|---|---|
| Phase 1: Partial Launch | End-November 2026 | Minimum capacity following completion of quay test runs |
| Phase 2: Mid-Scale Expansion | September 2027 | Arrival of first 15 straddle carriers; 50% capacity readiness |
| Phase 3: Full Infrastructure | Q1 2028 | Second 15 straddle carriers; 100% infrastructure completion |
| Phase 4: Full Commercial Scale | Mid-2028 | Maximum container throughput operations |
Governance Shift and SLPA Operating Structure
To eliminate traditional state-sector procurement and operational bottlenecks without divesting strategic maritime assets, the government is incorporating a dedicated operating company 100% owned by the SLPA.
Kodithuwakku noted that authorities are also evaluating potential private-sector collaboration structures for the East Container Terminal to maximize foreign exchange earnings and operational efficiency. This dual-track approach mirrors regional port governance reforms aimed at retaining sovereign asset ownership while matching private terminal turnaround speeds.
Business & Economic Impact
Bringing the East Container Terminal online, even at partial capacity, relieves immediate berth congestion at the Port of Colombo alongside the private Colombo West International Terminal expansion. Colombo relies heavily on Indian subcontinent transshipment volumes, which account for over 75% of total port throughput.
For Sri Lankan exporters and logistics operators, added deep-water berth capacity reduces vessel waiting times and demurrage costs during peak shipping windows. Investors tracking listed maritime and logistics counters on the Colombo Stock Exchange market summary will watch whether SLPA’s new corporate subsidiary accelerates crane productivity ahead of the September 2027 straddle carrier delivery.